Technical issue delays Lamprell rig delivery

Offshore staff

SHARJAH, UAELamprell expects to deliver a newbuild jackup drilling rig next month, several months behind schedule.

The rig, which is in the final stages of commissioning, had undergone a series of equipment proving tests which brought to light a technical issue with components supplied by an original equipment manufacturer (OEM).

Otherwise, the workscope for making the rig ready for delivery is complete.

The resultant delay could leave Lamprell exposed to potential damages, although the board expects to recover the majority of the remedial costs from the OEM, using legal means if necessary.

All the other six rigs the company is constructing remain on schedule.

07/26/2016

Share your news with Offshore at news@offshore-mag.com

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Latest Articles

There is no current content available.

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...