Helix finalizes well intervention contract with Petrobras

Offshore staff

HOUSTON Helix Energy Solutions Group Inc. has completed its contract renegotiations with Petrobras, and has entered into amendments to its well intervention services contracts for its two chartered vessels, the Siem Helix 1 and the Siem Helix 2, offshore Brazil.

The contract for the Siem Helix 1, originally scheduled to begin no later than July 22, 2016, was amended to commence between July 22, 2016 and Oct. 21, 2016. The day rate under the contract has been reduced to a level acceptable to both parties.

The contract for the Siem Helix 2, originally scheduled to begin no later than Jan. 21, 2017, was amended to commence between Oct. 1, 2017 and Dec. 31, 2017. The day rate under this contract did not change.

Owen Kratz, president and CEO of Helix, stated: “We are glad to finalize this process in a manner that makes sense for both companies, and look forward to a long and productive working relationship.”

06/03/2016

Share your news with Offshore at news@offshore-mag.com

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...