Zora gas plant still in commissioning phase

Offshore staff

SHARJAH, UAEDana Gas says the new onshore gas processing facility receiving supplies from the Zora field offshore Ajman/Sharjah is currently producing at 60% capacity of 40 MMcf/d, with commissioning still in progress.

The previous maximum tested flow rate was 50 MMcf/d.

Zora began sales gas production on Jan. 14, 2016.

05/05/2016

Share your news with Offshore at news@offshore-mag.com

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...