McDermott progresses offshore Saudi Arabia installations

Offshore staff

HOUSTONMcDermott International has issued an update on its offshore construction programs in the Middle East.

The Saudi Aramco Karan 45 project has progressed ahead of schedule and the company has completed the Abu Ali cables project ahead of schedule.

Additionally, McDermott finished the offshore installation scope for Aramco’s Manifa field development project.

Execution has started of a lump-sum project awarded under Aramco’s recently awarded long-term agreement (LTA II). Fabrication of the 12 jackets is on track with three due to be loaded out and installed during the current quarter.

Following load-out and trans-spooling of the 54-mi (87-mi), 115kV submarine composite cable in the area for the Marjan Power Systems project, installation should get under way shortly.

02/23/2016

Share your news with Offshore at news@offshore-mag.com

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...