South Pars 20, 21 pipelay in shore pull phase

Offshore staff

TEHRAN, Iran – Iranian Offshore Engineering and Construction Co. (IOEC) says laying pipelines for phases 20 and 21 of the South Pars gas field in the Persian Gulf is close to completing the shore pull phase.

Director of pipeline projects Motalleb Afshari told news service Shana that pipelaying for the two phases should be completed in early December.

Two parallel 100-km (62-mi), 32-in. pipelines will transport gas to the Iranian shore. To date eight of the 11 planned wells have been drilled, he added.

In another Shana report, Pars Special Economic Energy Zone (PSEEZ) managing director Mehdi Yousef said development of all remaining phases of South Pars should be finished by March 2018.

A total of 29 phases are under development – currently the field is producing 450 MMcm/d of gas. Total reserves are estimated at 14 tcm of gas and 18 Bbbl of condensates.

06/03/2015

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...