CNOOC delivers gas from latest Dongfang development

Offshore staff

HONG KONG – CNOOC has begun production ahead of schedule from the offshore Dongfang1-1 gas field Phase I adjustment project.

The field is in the Yinggehai basin of the Beibu Gulf in the South China Sea, in an average water depth of around 70 m (230 ft).

To fully exploit the existing Dongfang1-1, the company added a wellhead platform connected to seven producing wells.

Currently five wells are producing a total of 53 MMcf/d slightly below the planned plateau.

06/11/2015

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...