Arendal Spirit heads to Brazil

Offshore staff

HAMILTON, Bermuda – Teekay’s Arendal Spirit is on its way via heavy-lift vessel from COSCO in China to a three-year contract with Petrobras offshore Brazil.

The maintenance and safety facility has 2,000 sq m (21,528 sq ft) of deck area, accommodations for 500 personnel; three cranes; and a variable deck load of 4,500 tons.

04/14/2015

Arendal Spirit
Arendal Spirit aboard heavy-lift vessel. (Courtesy Teekay)

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...