South Pars Phase 13 jacket heads offshore Iran

Offshore staff

TEHRAN, Iran – The fourth platform jacket for Phase 13 of the South Pars gas field development has been loaded out, according to new service Shana.

Pars Oil and Gas Co. expects to install the jacket, constructed by Iranian Marine Industrial Co. (Sadra), over the next few days.

 The structure weighs 1,995 tons and is more than 72 m (236 ft) tall.

Phase 13, now more than 50% complete, is under development by a consortium of Petro Paydar Iranian, Sadra, and MAPNA on an engineering, procurement, and construction basis.

10/10/2014

Fourth platform jacket for Phase 13 of the South Pars gas field development

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...