Papa Terra TLP in place offshore Brazil

Offshore staff

HOUSTON – McDermott has completed installation of the extended TLP on the Papa Terra field for Petrobras. This is the first deepwater dry tree project offshore Brazil.

The construction vessel DB 50 has since demobilized from the field.

Elsewhere, McDermott expects to complete remaining offshore work on Azerbaijan’s COP project in the Caspian Sea by mid-May.

In the Far East, fabrication operations in Batam, Indonesia, are on track for INPEX’s Ichthys project off northwest Australia. Offshore installations are expected to start during 3Q 2014.

Off Malaysia, McDermott completed pipe and subsea structure installations for the Siakap project and the North Ocean 105 vessel has demobilized from the field. Mechanical completion is imminent.

The company describes its program as “a major technical achievement of complex pipe-in-pipe and subsea structure installation in over 5,000 ft [1,524 m] of water.”

04/01/2014

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...