GALVESTON, Texas – Development of the Tubular Bells field is proceeding on schedule, with the drilling campaigns under way and construction of the spar platform ongoing. Project operator Hess Corp. (NSE:HES) provided an update at the Topsides conference being held in Galveston, Texas.

The drilling program began last year, and the Stena Forth has been onsite since April. To date, it has drilled nine topholes and is currently drilling the second well. When the drilling program concludes, the project will have three to five producers, and two to three water injection wells.

Construction of the spar platform is underway in Texas and Louisiana. The engineering and construction of the project is being conducted almost entirely within the United States.

The initial subsea development will comprise two drill centers connected to three production wells and two water injection wells. There is a possibility that two additional production wells and one additional water injection well may be added to the field development.

The subsea facilities will be tied back to a Williams Partners-owned floating production spar (FPS) with a 50-person accommodation capacity. Hess will initially operate the production facility.

The spar platform is designed to handle:

  • 60,000 b/d of oil
  • 135 Mcf/d of gas production
  • 40,000 bbls produced water treating capacity
  • 60,000 bbls of water injection per day.

Export from the FPS will be through Williams’ existing pipeline systems, including its 12-in. oil line and its 12-in. natural gas line.  

First production is planned for the 2Q 2014. The primary target lies at approximately 24,000 ft (7,315 m) reservoir depth below approximately 10,000 ft (3,048 m) of salt.

The Tubular Bells project was sanctioned in 2011 with Hess having a 57.14% working interest as operator. Chevron has the remaining 42.86% interest.

02/06/2013

Whitepapers

Survey Report: Smart Process Applications for a Mobile Workforce

In partnership with PennEnergy Research, OpenText surveyed energy companies in the oil and gas, p...

Top 20 Controls ICS Implementation Guide

Considering the complexity and scope of today’s critical control environment, compliance has beco...

Five Steps to Build an Effective Threat Intelligence Capability

Against today’s mutating threat landscape and sophisticated cybercriminals, security and risk (S&...

Big Data: Business Insight for Power and Utilities

With this paper Microsoft aims to distill the Big Data drivers, challenges, and opportunities for...