North Sea Brynhild heading for year-end start

Offshore staff

STOCKHOLM, Sweden – Development drilling has started on the Lundin Norway-operated Brynhild field in the Norwegian North Sea.

The jackup Maersk Guardian will drill four wells on the field in license PL148. The location is close to the Norway-UK maritime border, 210 km (130 mi) from the Norwegian mainland.

All the wells will be tied back subsea to the Haewene Brim FPSO serving Shell’s Pierce field, 38 km (23.6 mi) to the south. Drilling is expected to continue through 2Q 2014.

The subsea template/manifold and 38-km production pipeline have already been installed. Topside modification work is expected to start on the FPSO in July, with production from Brynhild likely to start this fall. Lundin estimates the field’s reserves at 23 MMboe, with production set to peak at 12,000 boe/d. The hydrocarbons will be processed at the FPSO before being offloaded for further transportation.

Lundin has a 90% interest in the development. Talisman Energy Norge holds the remaining 10%.

6/17/2013

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...