Comprehensive modeling/monitoring system for Laggan-Tormore

Offshore staff

ABERDEEN, UK – Total has contracted Kongsberg Oil & Gas Technologies to provide an operator decision support system for the Laggan-Tormore gas project west of Shetland.

The scope comprises design, build, installation, training, and support of a production management system (PMS) and an overall flow metering system (OFMS) based at the Shetland Gas Plant processing terminal.

The PMS is a dynamic model of the 140-km (87-mi) production pipelines and gas processing facilities that will allow the operator to understand and predict process behavior.

According to Kongsberg, a high-fidelity model is critical to manage the liquids inventory, and in particular the MEG inhibitor close loop system and its regeneration.

The dynamic models will use the latest version of LedaFlow, a new transient multi-phase flow simulator that Kongsberg has developed jointly with Total.

The OFMS is included to give better control of the production reconciliation, and to provide back-up to the multi-phase flow meters.

12/17/2012

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...