Ekofisk platform decks assembled

Offshore staff

TANANGER, Norway – ConocoPhillips Norge says all deck sections are now in place for the new Ekofisk 2/4 Z platform at Aker Solutions’ yard in Egersund, Norway.

Work on the topsides started on March 9, with full size reached after 223 days. Additionally, a 116-m (380-ft) bridge has been delivered to connect the platform to the rest of the Ekofisk complex in the southern Norwegian North Sea.

Further construction for the project continues at bases in Oslo, Houston, Poland, Spain, and Italy.

11/08/2012

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Shell Leverages Data to Transform from Reactive to Predictive Operations

This 6-page report describes how Shell engaged in a massive project with OSIsoft to transform the...

Selection, Use, Care and Maintenance of FR Clothing

For industries operating in an inherently dangerous environment, the importance of selecting the ...

Evolution or Revolution: IT / OT convergence means a world of possibilities

The oil and gas industry is experiencing a rapid paradigm shift in regards to digital transformat...

Predict, Prescribe, Profit: Creating a World that Doesn't Break Down

What are you doing to reduce unplanned downtime at your plant? Equipment breakdowns and process i...