Ekofisk platform decks assembled

Offshore staff

TANANGER, Norway – ConocoPhillips Norge says all deck sections are now in place for the new Ekofisk 2/4 Z platform at Aker Solutions’ yard in Egersund, Norway.

Work on the topsides started on March 9, with full size reached after 223 days. Additionally, a 116-m (380-ft) bridge has been delivered to connect the platform to the rest of the Ekofisk complex in the southern Norwegian North Sea.

Further construction for the project continues at bases in Oslo, Houston, Poland, Spain, and Italy.


Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Overcoming ICS Management Challenges

Customers confirm they save 80% of their time identifying, analyzing, and reporting ICS cybersecu...

Securing Industrial Control Systems: The Basics

Since isolation seems to be impossible for control system environments, how do companies protect ...

Case Study: Create a Sustainable NERC CIP Compliance Program

With over 100 endpoints, a large US generation and transmission utility was spending 2-3 hours co...