Subsea manifold repair restores flow to Troll

Offshore staff

STAVANGER, Norway – Hydratight has repaired a damaged pipe on a subsea manifold linked to Statoil’s Troll C oil and gas platform in the Norwegian North Sea.

A mandrel and its supporting pipe were pulled out of position during an operation, overloading the pipe. This necessitated shut-down of an associated 10-in. (25.4-cm) line, halting production.

Statoil commissioned Hydratight to supply a 6-in. (15.2-cm) super duplex Morgrip end-connector to fit within the physical constraints of the damaged manifold, 340 m (1,115 ft) subsea. This sealed the line, as required. Pipe integrity was retained with no de-rating of the pipeline or deviation from the original design.

The pipe – which carries a mixture of water, oil, and gas – was pressure-tested to 267 bar (3,872 psi) after the procedure, and will be tested again periodically to ensure no further deteriorated has occurred.

4/12/2012

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...