Nord Stream subsea tie-ins under way

Offshore staff

ZUG, Switzerland – Preparations have started for welding together two of the three sections of the first 1,224-km (760-mi) Nord Stream gas pipeline in the Baltic Sea.

They will be joined on the seabed in 80 m (262 ft) water depth off the coast of Finland under a process expected to take around two weeks. Technical completion of the first of the twin pipelines should be achieved in June, when the final section is welded onto the pipeline off the Swedish island of Gotland in 110 m (361 ft) of water.

The pipeline will operate without an intermediate compressor station, but with three different design pressures and pipe wall thicknesses to accommodate falling gas pressure during the journey from Russia to the landfall in northern Germany.

Connection of these three sections is being performed offshore where the design pressure changes from 220 to 200 bar (3,191-2,900 psi) and from 200 to 177.5 bar (2,900-2,574 psi), respectively.

Each will be gauged and pressure-tested before being joined via hyperbaric tie-ins and subsequently linked to the landfalls in Russia and Germany.

Technip is managing the hyperbaric tie-ins from its new DSV Skandi Arctic, using equipment supplied by the Pipeline Repair System (PRS) pool administered by Nord Stream partner Statoil.

The procedure takes place on the seabed in a specially created dry zone (underwater welding habitat). Welding operations are controlled remotely from the Skandi Arctic, with divers assisting and monitoring the subsea construction work.

Skandi Arctic transports and operates all equipment needed to move, lift, cut, and weld the pipeline sections together. Pipe handling frames move the pipe ends into tie-in position. They also can shift the pipeline sections sideways to line them up for welding.

05/11/2011



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...