South Pars 12 pipelay concludes

Offshore staff

TEHRAN -- Pars Oil and Gas Co. has completed the offshore pipelay for the South Pars Phase XII development, according to Iranian news service Shana.

The latest part of the program involved installing three lines, A, B, and C, with respective lengths of 149, 140, and 150 km (92/87/93 mi). Tie-ins will follow to the Phase XII platforms and onshore gas processing plants.

Project manager Rasoul Fallahnejad told Shana that the cost of laying three 32-in. (81-cm) and three 4-in. (10-cm) pipelines was around $900 million.

Overall, he added, the offshore program was 75% complete, with two rigs engaged in development drilling close to the A and C platforms. First production from this phase is scheduled for May 2012.

04/14/2011



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...