Guendalina on target for September start-up

Offshore staff

ROME -- Development of the Guendalina gas field offshore eastern Italy is on schedule with first gas expected in September, according to partner Mediterranean Oil & Gas,

Eni operates the project, in the AC 35 AG concession in the Adriatic Sea.

Construction of the jacket is complete, and installation should be completed during the next fortnight, subject to sea and weather conditions.

Work on the deck is also on schedule, with installation set to start immediately following completion of development drilling.

The two-well campaign for two wells should start in late March.

03/15/2011-



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...