Guendalina on target for September start-up

Offshore staff

ROME -- Development of the Guendalina gas field offshore eastern Italy is on schedule with first gas expected in September, according to partner Mediterranean Oil & Gas,

Eni operates the project, in the AC 35 AG concession in the Adriatic Sea.

Construction of the jacket is complete, and installation should be completed during the next fortnight, subject to sea and weather conditions.

Work on the deck is also on schedule, with installation set to start immediately following completion of development drilling.

The two-well campaign for two wells should start in late March.

03/15/2011-



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...