Phase two of rehabilitation and upgrade beginning at 40-MW Matala hydropower project in Angola

Sluice gates at 40-MW Matala hydro facility

On July 18, Empresa Publica de Producao de Electricidade (PRODEL) Project Manager, Celso Pontes, announced phase one at the 40-MW Matala hydroelectric project is complete and the detailed design of the second phase is now being prepared.

According to Pontes, phase two involves upgrading the current two turbine-generators and adding a third that will increase the plant’s total installed capacity. The amount of the increase and its cost has not yet been determined.

The facility is located on the Cunene River in the province of Huila, in central Angola, on the southwest coast of Africa.

Commissioned in 1954, in 2011 facility owner, PRODEL, awarded a US$249.6 million contract to Canada-based SNC Lavalin Inc. to improve the facility’s safety and its water storage capacity.

In April, HRW-Hydro Review Worldwide reported, “The rehabilitation of the Matala Dam was primarily necessary to ensure the stability and the structural safety of the dam, which was under risk of collapsing,” according to Pontes.

During phase one of the rehabilitation and modernization, in addition to the 29 sluice gates already in operation, a further eight were added. The additional gates allow for the regulation of the flow in a more precise way.

“The rehabilitation was also required to ensure the operation of the powerhouse generating capacity and the spillway control systems in order to improve the hydraulic discharge capacity,” he said

The principal works performed by SNCL included:

Construction of a new spillway equipped with eight radial gates; Rehabilitation of the concrete structure affected by alkali-aggregate reaction, which caused considerable swelling to occur; Evaluation (capacity and structural integrity) of the concrete bridge structure; Rehabilitation of the road bridge, including resurfacing of the deck and bearing rehabilitation; and Grouting works.

The Matala hydroelectric is located about 180 km from the city of Lubango in southern Huila province. 

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs