First unit approved at Belo Monte-associated Pimental hydropower plant

Pimental unit operating

Commercial start-up of the first generator at the 233-MW Pimental hydropower plant has been approved by Aneel in Brazil.

Pimental is part of the 11.2-GW Belo Monte plant. The complex is on the Xingu River in the northern state of Para.

The unit has installed capacity of 38.83 MW. In total, the Pimental powerhouse will contain six bulb turbines.

In February 2016, test operations were under way at Belo Monte’s 611.11-MW Generating Unit No. 1, and in April 2016 the first units began commercial operations.

Belo Monte was originally scheduled to begin commercial operation in February 2015. Developer Norte Energia estimates the US$26 billion project will be in full operation in January 2019.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs