Colombia’s Guatape hydro facility back on line after fire

Guatupe hydro online

Colombian utility Empresas Publicas de Medellin (EPM) brought two of the eight turbine-generator units at its 560-MW Guatape hydro facility back on line after a February fire.

The utility says emergency work to bring the remaining six units on line is advancing according to schedule, according to BNamericas. All eight units should be fully functional by September.

EPM says the Feb. 15 fire resulted from an incident with the cables that take electricity from the powerhouse to the substation.

The plant is in Antioquia Department of Colombia and was built in the late 1960s.

EPM owns 2,600 MW of generating capacity.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs