Work on 12-MW Tokwe-Mukosi hydroelectric facility to resume in March

Zimbabwe

In March, work is expected to resume on the unfinished US$255 million 12-MW Tokwe-Mukosi hydroelectric facility, located in Masvingo, Zimbabwe, if the Zimbabwean government can raise $60 million needed to complete the facility’s dam and pay contractors.

Construction on the facility initially began in 1998, but lack of funding halted work in 2008 according to published reports. Construction at the site resumed in 2011, but stopped again in December due to a lack of funding.

The facility is home to the Tokwe Mukorsi Dam, an unfinished concrete-face rock-fill dam on the Tokwe River, just downstream of its confluence with the Mukorsi River, about 45 mi south of Masvingo.

Current contractor, Italy-based Salini Impregilio, began work at the site in 2008, but since that time numerous issues including funding, environmental and political situations have interrupted construction.

According to local reports, Tokwe-Mukosi Dam was about 90% complete when work stopped.

Zimbabwe National Water Authority (ZNWA) marketing manager Marjorie Munyonga on Feb. 4 reportedly said $60 million is needed to complete outstanding work at the dam and pay Salini Impregilio.

The latest funding increment is needed to complete work on fortifying the upstream side of the dam wall and construction of the right bank spillway tunnel and penstocks.

Munyonga said construction work would resume at the end of March, which is when the rainy season should end.

"Work on the construction of Tokwe-Mukosi Dam is expected to resume soon after the rainy season,” she said. “This is so because part of the outstanding works, which is the outlet works, cannot be carried out while there is still some water passing through."
 

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs