Feasibility study under way for Thakot hydropower project in Pakistan

WAPDA studying Thakot hydro

The Water & Power Development Authority (WAPDA) in Pakistan has awarded a contract to Lahmeyer International to prepare a feasibility study for the Thakot hydropower project.

The project, on the Indus River, will have a capacity of 2,000 MW to 2,500 MW, according to a press release from Lahmeyer. However, WAPDA’s website says the project will have a capacity of 4,000 MW and produce mean annual energy of 21,300 GWh for the national grid.

The project is to have a gross head of 185 meters and a design discharge of 2,900 cubic meters per second. A 28-km-long power tunnel will feed water to eight Francis turbine-generator units.

Approved cost of the project was PKR719.628 million (US$6.87 million) in 2012.

WAPDA is an autonomous and statutory body established in 1958. WAPDA’s mandate is development of water and hydropower resources in an efficient manner. The authority plans to construct five multi-dimensional water storage dams during the next three to 12 years that will also provide inexpensive and clean hydroelectricity.

Projects ongoing by the company include installation of the 1,410-MW Tarbela 4th Extension on the Indus River, refurbishment of the 1,000-MW Mangla power station on the Jhelum River, construction of the 969-MW Neelum Jhelum hydropower project on the Neelum River, construction of Diamer Basha Dam on the Indus River, construction of the 2,160-MW Dasu hydropower project on the Indus River, and installation of the 1,410-MW Tarbela 5th Extension on the Indus River.

The company also has future work planned at 11 hydropower facilities, including rehabilitation and new development.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs