Pakistan seeks highway move, access road for 2,160-MW Dasu Stage 1 hydro project

Pakistan Map

Pakistan's Water and Power Development Authority (WAPDA) invites applications for pre-qualification to relocate a highway and to construct an access road for the 2,160-MW Dasu Stage 1 hydroelectric project on Pakistan's Indus River. Responses to two solicitations are due March 24.

WAPDA previously called for applications for pre-qualification by February 27 to perform major civil works construction of Dasu Stage 1. It took expressions of interest in August for project management and for an ecological-biodiversity plan for the project. Pakistani Prime Minister Nawaz Sharif broke ground in June for the total 4,320-MW Dasu Stage 1 and 2 project in Kohistan District.

Dasu Stage 1 includes construction of a 242-meter-tall roller-compacted-concrete dam, underground powerhouse and switchgear cavern, and six turbine-generators. About 34 villages with 7,000 people are to be relocated and 4,104 hectares to be inundated.

WAPDA now invites applications for pre-qualification for two lots:

  • ICB NO. DASU-KKH-02, Relocation of Karakoram Highway from RD 25+200 to RD 62+032; and
  • ICB NO. DASU-RAR-02, Construction of Right Bank Access Road from Dam Site to Uttargah.

Invitations to bid for both lots are expected to be issued in May.

Pre-qualification documents, in English, for each lot may be purchased from the address below upon written application and a fee of 5,000 rupees or US$50 with mailing of documents within Pakistan. For mailing of documents outside Pakistan, the fee is 10,000 rupees or US$100. Payment is by bank pay order or demand draft to General Manager, Dasu HPP, WAPDA.

Applications for pre-qualification for each lot are due by 11 a.m. March 24, labeled either "Application to Pre-qualify for Dasu Hydropower Stage I Project Procurement of Works ICB NO. DASU-KKH-02, Relocation of Karakoram Highway from RD 25+200 to RD 62+032" or "Application to Pre-qualify for Dasu Hydropower Stage I Project Procurement of Works ICB NO. DASU-RAR-02, Construction of Right Bank Access Road from Dam Site to Uttargah."

For information, contact General Manager/Project Director, Dasu Hydropower Project, Water and Power Development Authority (WAPDA), 5th Floor, Al-Malik Plaza, Davis Road, Lahore, Pakistan; (92) 42-99202676; Fax: (92) 42-99202667; E-mail: dasuhpp@yahoo.com; Internet: www.wapda.gov.pk, www.ppra.org.pk, www.worldbank.org.
 

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs