Work complete at Vietnam's 2,400-MW Son La hydroelectric project

All six turbines at Vietnam's 2,400-MW Son La hydropower plant have been connected to the national grid, marking the completion of the nation's largest hydroelectric project.

Work on the US$2.5 billion project began in 2005, with the previous five Francis-type turbines being put into service incrementally throughout the construction process.

Already, Electricity of Viet Nam (EVN) says the Son La complex has contributed about 11,400 GWh to the grid, adding a reported $55 million back to the Son La Province's budget.

The Son La project includes a 453 feet by 300 feet concrete dam that impounds the Da River in north Vietnam.

Also in Vietnam, HydroWorld.com reported in September that Trung Son Hydropower Co. Ltd. is seeking equipment for the 260-MW Trung Son project on the Ma River.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs