Federal court halts work on Brazil's Teles Pires hydropower project

BRASILIA, Brazil 3/30/12 (PennWell) -- Brazil's federal court has suspended work on the 1,800-MW Teles Pires hydroelectric project in the country's Amazon basin, state news service Agencia Brasil says.

The decision voids the installation license awarded by Brazil's environment regulator, Ibama, in August 2011.

Agencia Brasil says the irregularities identified by the court include a lack of prior consultation with indigenous groups, which is in conflict with both Brazilian and international law.

The court says it will fine project owner Teles Pires Energia Eficiente US$55,000 per day should it not comply with an immediate suspension of natural rock explosions.

The project is now in limbo as the government is deciding whether to uphold the court's restraining order.

Teles Pires Energia Eficiente is a consortium that is comprised of utility holding company Neoenergia, state-run utilities Eletrobras Furnas and Eletrobras Eletrosul, and engineering company Odebrecht.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs