14,000-MW Itaipu hydro project shores up dispatch with new transformer

Itaipu Binacional, which operates the 14,000-MW Itaipu hydroelectric power project on the Brazil-Paraguay border, announced a 375MVA transformer regulator has begun operations.

The unit, dubbed TxRx, is the 14,000-MW hydropower project's fifth and aims to bolster supply to Paraguay in the lead-up to the planned Itaipu-Villa Hayes transmission project, Business News Americas reported.

Consortium ABB-CIE supplied and installed the TxRx under a US$17.7 million contract.

To buttress Itaipu's transformer infrastructure even more, Itaipu earlier this year awarded consortium WEG-Tecnoelectric a US$11.4 million contract to supply a reserve transformer. This equipment is due to be in place in 2012.

For more hydropower news and information, click here

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs