Japan finds costs are ballooning for dismantling Fukushima

Fukushima

TOKYO (AP) — Japan's estimate of dismantling the Fukushima nuclear plant is ballooning far beyond the utility's estimate of $19 billion.

A government study released Tuesday found decommissioning the Fukushima Dai-ichi plant already has cost $770 million over the last three years.

The plant suffered multiple reactor meltdowns due to damage from the March 2011 earthquake and tsunami.

The ministry overseeing nuclear power said the decommissioning costs will continue at several hundreds of billions of dollars a year.

Tokyo Electric Power Co., the utility that operated and is now decommissioning Fukushima Dai-ichi, has said decommissioning will take several decades.

Even if it were to take 30 years at an estimated annual cost at $3 billion, both conservative projections, the cost would be nearly $100 billion.

TEPCO spokesman Shinichi Nakakuki declined comment on the government projection, but he acknowledged TEPCO was still trying to determine what exactly the decommissioning effort might involve.

"It is difficult to calculate the entire cost for the decommissioning," he said, adding that the 2 trillion yen figure had so far taken into account the effort to remove the nuclear debris, taking the example of Three Mile Island in the U.S., as well as costs and equipment needed to keep the reactors stable.

The study did not distinguish between costs borne by the government and borne by TEPCO, which received a government bailout.

Japan has been struggling to clean up parts of the no-go zone to put the worst nuclear catastrophe since Chernobyl behind it.

The government has estimated that decontaminating the areas around the Fukushima plant, including removing radiated topsoil, buildings and trees, will cost at least $24 billion.

But experts have been warning that such estimates may be too optimistic. The nuclear disaster in Fukushima displaced about 150,000 people.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs