FirstEnergy substation project to boost reliability for customers in Ohio

distribution transformer substation security elp

FirstEnergy Corp. is expanding a transmission substation in Leroy Center to help reinforce the electric system, support load growth and enhance reliability in The Illuminating Co.'s northeast Ohio service area.

The project includes installing circuit breakers and two massive electrical transformers, each weighing about 368 tons and measuring about 28 feet tall by 25 feet wide and 44 feet in length. 

Transformers are used to convert power from 345 kV to 138 kV as it moves along the transmission system.  Specialized "smart" communications equipment also was installed at the substation to remotely monitor operations.

A nearby 345 kV transmission line connecting the Perry Nuclear Power Plant to a substation in Cleveland also will be connected to the substation in Leroy Center as part of this project to enhance resiliency and operational flexibility.  The overall cost of the project is about $24 million, with about $14.8 million projected to be spent in 2016.  The in-service date for the expanded substation is June 1, 2016.

"By connecting this substation to an existing transmission line, we are able to create another cost-effective option when it comes to delivering safe and reliable power to our customers," said John Skory, regional president of The Illuminating Co.  "In addition, the high-tech substation devices we plan to install will give us the ability to operate the system remotely, automatically resetting the equipment instead of having to send a line crew to investigate the cause of the problem."

The project is funded and owned by American Transmission Systems, a FirstEnergy transmission company.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs