Texas 3,400 MW, gas-fired power plant moves forward

Panda Sherman Power Plant

FGE Eagle Pines is nearing issuance by the Texas Commission on Environmental Quality of a state air quality permit, prevention of significant deterioration air quality permit and a greenhouse gas PSD air quality permit that would authorize construction of the FGE Eagle Pines Project, a natural gas-fired combined-cycle turbine power plant.

The project site is at New Summerfield in Cherokee County, Texas. The commission said in a Sept. 10 public notice, posted to its website on Sept. 15, that a decision has been made to issue these permits, with comments being taken on that proposed action.

This permitting authorizes six Alstom GT36 natural gas fired combustion turbines each rated at a nominal 321 MW and equipped with a duct burner fired heat recovery steam generator. Each combustion turbines shaft drives an electric generator and each heat recovery steam generator supplies steam to a single steam turbine which drives a third electric generator.

The combustion turbines may employ evaporative cooling and/or inlet high fogging for power enhancement. Each heat recovery steam generator is equipped with natural gasfired duct burners. The duct burners in each heat recovery steam generator are limited to a maximum heat input of 799 million British thermal units per hour (MMBtu/hr), based on the high heating value of the fuel.

The FGEEP Project will include three natural gas-fired combined cycle power blocks, each block comprised of two gas-fired combustion turbines, two supplemental fired duct burners heat recovery steam generators, and one steam turbine. Each heat recovery steam generator is to be equipped with DBs that will have a maximum design heat input capacity of 799 million British thermal units per hour (MMBtu/hr). The combustion turbines and DBs are to be fueled with pipeline quality natural gas.

Each power block will also have a steam turbine generator designed to produce about 502 MW with the additional duct firing. Each of the three blocks will include the following ancillary equipment: one multi-cell condenser/cooling tower, one emergency generator, one firewater pump, two diesel storage tanks, and pressurized aqueous ammonia storage tanks. Additional emission sources include fugitives from natural gas and ammonia piping and circuit breakers.

The construction of the first of the three power blocks of the FGEEP Project is planned to begin in the spring of 2016. Construction of the subsequent two power blocks are planned to begin fall of 2016 and winter of 2017. Base load generation of the proposed electric generating facility after all three blocks have been built will be a nominal rating of about 3.4 GW.

That is contact information for FGE Power. The company's website shows that the twin, 747 MW (each) FGE Texas 1 and 2 projects are being developed in Mitchell County, Texas, but doesn't show the FGE Eagle Pines project.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013