Natural gas power plants across U.S. make progress in September

gas power plant construction elp

Developers of new natural gas power plants made headway with licensing, equipment and vendors during mid-to-late September, according to information gathered by GenerationHub.

Here are some recent developments on projects of at least 50 MW:

LS Power affiliate Hickory Run Energy proposed a natural gas generating facility located in Lawrence County, Pa. The facility will have a total capability of 1,000 MW with 870 MW of this output being recognized by PJM Interconnection as capacity. A PJM study on the project, dated September 2015, said the proposed in-service date for this project is June 2018.

•Public Service Enterprise Group unit PSEG Power has ordered a General Electric gas turbine and associated equipment for its new Sewaren 7 combined-cycle power plant in New Jersey. The facility is expected to generate 540 MW. PSEG Power had announced Aug. 24 that Sewaren 7, a new 540 MW, dual-fuel combined-cycle power plant, had cleared PJM's Reliability Pricing Model Base Residual Auction. PSEG expects to begin construction on the $600 million plant in early 2016. The project is targeted for commercial operation in the summer of 2018.

•Braintree Electric Light Department on Sept. 28 filed with the Federal Energy Regulatory Commission an interconnection agreement that covers the addition of a 66 MW simple-cycle combustion turbine (Watson Unit 3) at the site of the existing Watson Units 1 and 2. The Massachusetts utility also owns and operates the Potter 2 facility, which will be retired when this new unit begin operations.

•Renovo Energy Center, based in Frederick, Maryland, has filed an application with the Pennsylvania Department of Environmental Protection for an air permit for the 950 MW Renovo Energy Center. The project would be a combined-cycle power plant to be located in the Borough of Renovo in Clinton County, Pa., according to a notice in the Sept. 26 Pennsylvania Bulletin.

•A domestic affiliate of Advanced Power Services AG is asking the New York State Department of Environmental Conservation for an updated draft air permit for the 1,000 MW Cricket Valley Energy Center. The project would be located in Dutchess County, New York. The initial permit was issued in September 2012, but is due to lapse. The state agency is taking comments until Nov. 17.

•Newark Energy Center, EIF Newark and other related companies informed FERC on Sept. 22 that the new 755 MW Newark Energy Center facility is about ready for commercial operation. The facility is interconnected to the transmission system owned by Public Service Gas & Electric and operated by PJM Interconnection.

•Burns & McDonnell on Sept. 17 said that it is teaming with Skanska USA and Ecco III Enterprises Construction to design and construct a new 720 MW combined cycle facility in Wawayanda, New York. The vendors have been retained by an affiliate of Competitive Power Ventures to develop the CPV Valley Energy Center.

•The Pennsylvania Department of Environmental Protection officially announced Sept. 17 that it has issued an air quality plan approval for Moxie Freedom Energy to construct and operate a 1,050 MW natural gas-fired plant in Salem Township, Luzerne County. The approval was granted by DEP’s Air Quality Program on Sept. 1. The project is currently forecast to start commercial operation in the second quarter of 2018.

•The Ohio Power Siting Board on Sept. 17 authorized Clean Energy Future-Lordstown to construct an 800 MW natural gas-fired combined-cycle generation facility in Lordstown, Ohio. The company plans to start construction later this year and begin commercial operation by May 2018. The project represents an estimated construction investment of more than $850 million.

•FGE Eagle Pines is nearing issuance by the Texas Commission on Environmental Quality of air permits that would authorize construction of the 3,400 MW FGE Eagle Pines Project, a natural gas-fired combined-cycle plant. The project site is at New Summerfield in Cherokee County, Texas. The commission said in a Sept. 10 public notice that a decision has been made to issue these permits, with comments being taken on that proposed action.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013