Kemper power plant overruns climb another $25 million

Kemper county power plant

JACKSON, Miss. (AP) — Mississippi Power Co. said Tuesday it will spend at least another $25 million to finish the power plant it's building in Kemper County, pushing total costs to nearly $6.3 billion.

Jeff Shepard, a spokesman for the unit of Atlanta-based Southern Co., said the money will pay for further "startup and commissioning activities, as well as operational readiness."

Mississippi Power says the company, not its 186,000 customers, will cover the additional money. Customers this month are resuming paying 18 percent higher rates for Kemper after Mississippi regulators granted an emergency rate increase when Mississippi Power said it was running out of money.

That came after Kemper opponent and Southern District Democratic PSC candidate Thomas Blanton won an appeal to the state Supreme Court to overturn an earlier 18 percent rate increase and force $350 million in refunds.

The plant and associated lignite coal mine were originally supposed to cost $2.8 billion at most, but customers could pay almost $4.2 billion if the Mississippi Public Service Commission allows. The utility is absorbing more than $2 billion in overruns.

Also Tuesday, the commission unanimously denied an attempt by Blanton to dismiss the rate increase request. Though commissioners granted an emergency request by Mississippi Power to start collecting on $1.1 billion in equipment, including turbines that have been generating power since last year using natural gas, they still must make the increase permanent.

Blanton's lawyer, Michael Adelson, said he wasn't surprised by the move, as commissioners had already scheduled a Nov. 10 hearing to examine the prudence of Mississippi Power's spending and a Dec. 8 deadline for a decision.

Blanton has filed a fresh appeal asking the state Supreme Court to overturn the new rate increase. He says it's an end-run around the earlier ruling because at least some of the money would be used to build Kemper without an advance hearing on the company's spending.

"A duck is still a duck, even if you call it a 'turkey,'" the appeal states. "This is still another brazen attempt by Mississippi Power Co. to ignore the Supreme Court's June 11, 2015 opinion."

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs