Duke Energy to announce route for Foothills Transmission Line

Duke Energy Linemen

Duke Energy will announce its recommended route for a new transmission line between Campobello, S.C., and Asheville, N.C., in early October, three months earlier than originally planned.

Duke Energy considered a series of possible line segments for the new nearly 40-mile transmission line to ensure environmental and community impacts could be minimized as much as possible.

"We've been listening closely to potentially impacted communities and landowners along the study routes and have heard overwhelmingly from them the need to expedite the review process to reduce the period of uncertainty for selecting the final route," said Robert Sipes, Duke Energy's Western North Carolina regional general manager. "We've expanded our team, accelerated the schedule and are committing to complete our comprehensive process for route selection by early October.

The 230-kV power line will connect the western Carolinas region and Duke Energy's new Asheville power plant to a substation to be built in Campobello, S.C. It is a key part of the company's $1.1 billion Western Carolinas modernization project that includes replacing Asheville coal-fired plant with a new natural gas power plant.

According to Duke Energy, the project will reduce emissions and water use and help meet the growing power demand in the Western Carolinas. Based on current natural gas prices, it will also produce electricity 35 percent less expensively and significantly enhance long-term power reliability in the region.

The utility previously extended its public comment period on the route options to Aug. 31.

The company has held three public meetings on the project and received almost 3,000 comments to date.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs