ISA, Transelec win Chile transmission line contracts

Chile's central grid operator CDEC-SIC awarded Colombia's ISA and local group Transelec contracts to build and operate transmission infrastructure on the country's main grid, according to Business News Americas.

ISA picked up 500/200 kV 750 MVA autotransformer banks for new substations Cardones, Maitencillo and Pan de Azúcar which will require a combined $75.8 million, CDEC said in a statement. ISA will receive $2.62 million/year when operations begin.

Transelec won a contract to build a third 500/220kV 750 MVA autotransformer bank at the Alto Jahuel substation. Investment reaches $44.7 million and the company will receive $3.06 million/year.

The Chilean group also picked up new 220 kV line Lo Aguirre-Cerro Navia that will cost $54.6 million. Transelec will receive $9.59 million/year.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs