Southern Co. Kemper CCS project will take longer, cost more than anticipated

Utility company Southern Co. pushed back the date of completion for its 582 MW Kemper coal-fired power plant to the last quarter of 2014 while at the same time increasing the projected cost of the project again, to north of $4 billion.

Kemper is an integrated gasification combined cycle project (IGCC) designed to turn coal into synthetic gas. The project's carbon capture capacity will also capture at least 65 percent of the carbon dioxide that results from combustion of the syngas. The captured carbon will be used for enhanced oilfield extraction.

Southern Co. said the revised date of completion is because of wetter than expected weather as well as installation levels that were lower than anticipated.

According to Reuters, the project's stated $4.02 billion price tag can rise to about $5 billion when you account for the cost of the coal mine, federal investments and the carbon dioxide pipeline network.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs