MOESK to rebuild Moscow substation

Moscow United Electric Grid Co. (MOESK) launched a comprehensive reconstruction of the 110 kV Electrostal substation in the east of the Moscow area in August.

The scope of the rebuilding project calls for the replacement of a pair of 60-year-old transformers, nine 110 kV oil circuit breakers and eleven 35 kV oil circuit breakers.

MOESK and contractors will replace the old transformers with modern gas-insulated ones will be installed, which are more efficient, safer and more environmentally friendly, according to the company.

The project is implemented within the framework of the MOESK’s investment program. The project will be implemented over the next three years; the total amount of financing will exceed $22 million.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs