LIPA to upgrade transmission line

New York City, July 19, 2012 — The New York State Public Service Commission has granted a certificate of environmental compatibility and public need to the Long Island Power Authority (LIPA) that will allow the utility to increase the design capacity of the existing 10.6 mile Wildwood to Riverhead electric transmission line from 69 kV to 138 kV.

The line is about 10.6 miles long and uses about 170 structural poles. The width of the right-of-way is about 100 feet. LIPA proposed to upgrade the transmission line from 69 kV by installing insulators capable of supporting 138 kV transmission using existing conductors and poles.

About 300 feet of underground 138 kV cable will be installed near the Wildwood Substation to transition the overhead line into the Wildwood Substation. LIPA states that no additional property rights will need to be acquired for the project.

Based on forecasted load growth, LIPA says the project will be needed prior to summer 2013. Demand on Long Island's East End has increased over the six-year period between 2000 and 2006 by an annual average of 5.2 percent. LIPA forecasts demand to increase on the South Fork at an annual average rate of about 3.3 percent through 2025. The project is a significant component of LIPA's plans to reinforce the existing transmission capacity of the South and North Forks of Long Island.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs