Commissioning of geothermal power plant to begin

U.S. Geothermal Inc. announced that its construction contractor has provided a notice of mechanical completion for the first of three 7.3 net MW, air cooled power plant modules at the Neal Hot Springs project in Oregon. The total project is about 90 percent complete with some 65 percent of the $96.7 million U.S. Department of Energy loan guarantee already drawn down to fund construction.

Mechanical completion of the first module marks the beginning of commissioning activities on various individual power plant components, controls and the related production and injection well-field. Once these commissioning activities are complete, the power module will undergo acceptance testing, leading up to full module startup and continuous operation.

The second power plant module is expected to achieve mechanical completion around June 7 and the third module is slated to achieve mechanical completion by the end of June 2012. The 22 MW net power plant is expected to achieve full commercial operation late in the third quarter of 2012.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs