FPL to invest $200 million to strengthen electric grid

Juno Beach, Fla., March 1, 2012 — Florida Power & Light Co. plans to invest more than $200 million in 2012 to strengthen the electric grid against major storms and keep service reliability high, the company said in an annual filing with the Florida Public Service Commission.

In 2012, FPL is continuing to invest in efforts to strengthen the infrastructure against severe weather and maintain its strong everyday reliability. In 2011, FPL continued to take steps to strengthen its electrical infrastructure and to enhance its emergency response capabilities.

Included in this ongoing work were pole inspections, system infrastructure hardening, vegetation management as well as other storm preparedness initiatives.

Pole inspections: In 2012, the company plans to inspect 137,000 distribution poles and reinforce or replace those that no longer meet the company's stringent standards for strength. FPL also plans to begin a new six-year cycle of inspections of its transmission structures and complete any and all remaining follow-up work identified during the 2011 inspections. In 2011, FPL replaced more than 10,000 utility poles after inspecting them for strength. This includes poles along local (distribution) and main (transmission) lines.

System hardening: In 2012, FPL will continue strengthening projects for feeders (main lines) that serve critical infrastructure facilities such as hospitals and 911 centers and important community needs such as grocery stores, gas stations and pharmacies, as well as for major highway crossings. In 2011, FPL completed the strengthening of its electric infrastructure serving virtually every existing 911 and emergency operations center in its service territory as well as other critical facilities identified with the help of local community leaders.

Storm preparedness: In 2012, FPL will continue its approved cycle plans to clear more than 12,000 miles of vegetation from its distribution lines and clear all of its transmission rights of way. In 2011, FPL executed its robust line-clearing plan and was able to clear additional fast-growing trees that were most likely to cause interruptions before the next scheduled trimming cycle.

In addition, FPL conducts extensive training for employees, focusing on restoring power after a storm. Each May, FPL simulates a major hurricane for the purpose of a company-wide storm drill to strengthen its storm-response plans.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs