Construction company, J Murphy & Sons, has completed the first phase of work on the UK’s first reheat biomass combined heat and power plant.

The Construction Index reports that at the £138m Cramlington plant in Northumberland, Murphy has installed more than 6,600 metres of cable ducts in preparation of installing the 66kV circuit in early 2017.
Murphy
The combined heat and power biomass plant uses reheat technology, which is relatively new to power plants of this size. Fuelled by new and recycled wood, steam will be led through two heating processes and two turbines, instead of one. This improves fuel efficiency, achieving a higher output.

The Cramlington plant will have an output of 27.8 MW, generating 223 GWh of renewable electricity.

Burmeister & Wain Scandinavian Contractors (BWSC) awarded Murphy a subcontract in October 2015 for the cabling and civils design stage, civil duct route construction, substation and compound construction and fit-out, as well as commissioning and installing the 66kV equipment and cable systems. 

Work is scheduled to be completed in summer 2017.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...