A Combined Heat & Power (CHP) Plant is to be developed at the Midvale Complex, North Philadelphia, USA, after the Southeastern Pennsylvania Transportation Authority (Septa) approved two new sustainability projects.

At an estimated cost of US$26.8 million, a natural gas-fired CHP plant will power part of SEPTA's Regional Rail system and its largest bus garage - financed entirely through energy savings guaranteed to SEPTA under the Pennsylvania Guaranteed Energy Savings Act (GESA).
SEPTA has selected Noresco, LLC as the energy services company to design the proposed CHP plant, which would use twin natural gas generators to power the Wayne Junction Substation and Midvale Bus Garage.

Noresco will now conduct an audit to determine the optimal configuration of the CHP Plant. Excess heat from the CHP plant will cover the heating load at three additional nearby SEPTA facilities. Given regulatory approvals the plant could be operational by 2017.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...