GE turbines installed at Australian iron ore mine

Fortescue Metals Group has opted for LM6000-PF aeroderivative gas turbine technology from GE for its Solomon 1 plant, and is part of Fortescue’s US$8.4 billion, three-year expansion in Western Australia’s iron-rich Pilbara region announced last year.

GE will supply two LM6000-PF dual fuel gas turbine packages, associated balance of plant and services for Fortescue’s new 120 MW power plant.

The LM6000-PF technology is the next generation of GE’s dry low emissions technology and the company claims it can deliver more than 40 MW at more than 40% efficiency at 25 °C while maintaining 25 ppm nitrous oxide levels. It is also able to achieve full generating capacity within 10 minutes.

The gas turbine packages will be shipped from Houston, Texas, US, in December 2011 and installed the following March. The plant is scheduled to enter commercial operation in the third quarter of 2012.

The units will run on diesel fuel initially and then switch to gas when the gas pipeline is available.

For more On-Site Power news click here.

For more Equipment & Technology news click here.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...